Flood Control and Drainage24FH0044

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES, MACUTAL RIVER (RIZAL SECTION), BARANGAY RIZAL, BARAS, CATANDUANES

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES, MACUTAL RIVER (RIZAL SECTION), BARANGAY RIZAL, BARAS, CATANDUANES is a DPWH-tracked public work in Catanduanes DEO, Region V. Reported contract value: ₱48,248,760.00. Status: Reported complete (DPWH). Contractor on record: AL-JON CONST DEVELOPMENT INC FORMERLY: ALJON CONST. Figures trace to dpwh.

Catanduanes DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱7,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Tubli and Barangay Dariao, Caramoran, Catanduanes
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Catanduanes DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

100 projects · ₱1.8B total · 0 flags

4. Implementation

Contract Amount

₱48,248,760.00

Progress

Reported complete (DPWH)

Start Date

May 23, 2024

Target End

December 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.