Flood Control and Drainage24CC0637

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY DAUNGAN (PUROK 1 TO PUROK 3), GUIGUINTO, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY DAUNGAN (PUROK 1 TO PUROK 3), GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱74,112,343.62. Status: Past target date (DPWH On-Going). Contractor on record: SYMS CONST TRADING. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱74,112,343.62

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

September 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.