Flood Control and Drainage23HO0262

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DIKE AT VALENCIA RIVER (DOWNSTREAM LEFT SIDE), ALEGRIA, C

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DIKE AT VALENCIA RIVER (DOWNSTREAM LEFT SIDE), ALEGRIA, C is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱67,446,717.99. Status: Past target date (DPWH On-Going). Contractor on record: ZLREJ TRADING AND CONST CORP. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23HO0262 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · imagery 2018-06-04 → 2018-06-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Cebu

Based on the coordinates published with the DPWH record and NOAH file Cebu.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DIKE AT VALENCIA RIVER (DOWNSTREAM LEFT SIDE), ALEGRIA, C

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Wall Structures along Sitio Parale (Right Side), barangay Sorsogon, Malabuyoc, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 7th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

119 projects · ₱8.5B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CEBU SOUTH COASTAL RD - (S00015CB) CHAINAGE 510 - CHAINAGE 1019

Region VII, Region VII

2025₱221.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CEBU SOUTH COASTAL RD - CHAINAGE 0 - CHAINAGE 510

Region VII, Region VII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURES AT BRGY. GUINTABOAN, UBAY, BOHOL

Region VII, Region VII

2024₱192.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, CANSAGA BAY BR. (B00613CB) ALONG CANSAGA BAY BRIDGE, CEBU

Region VII, Region VII

2022₱173.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, VIADUCT BR. (B00081CB) ALONG CEBU SOUTH COASTAL RD

Region VII, Region VII

2024₱173.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MARCELO FERNAN BR. (B00619CB) ALONG MARCELO B. FERNAN BR. & APPROACHES

Region VII, Region VII

2024₱173.7M
Reported complete (DPWH)
View all 119 projects →

4. Implementation

Contract Amount

₱67,446,717.99

Progress

Past target date (DPWH On-Going)

Start Date

December 27, 2023

Target End

September 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)CebuAlegriaValencia
Storms whose wind field reached it
Penha 2026Koto 2025Kalmaegi 2025
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.