Flood Control and Drainage23A00441

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG MARUSAY RIVER AND TRIBUTARIES, CALASIAO, PANGASINAN (PACKAGE 1)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG MARUSAY RIVER AND TRIBUTARIES, CALASIAO, PANGASINAN (PACKAGE 1) is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱96,498,738.20. Status: Reported complete (DPWH). Contractor on record: JHI CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,498,738.20

Progress

Reported complete (DPWH)

Start Date

January 22, 2024

Target End

November 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.