Construction of Flood Mitigation Structure23F00115

Construction of Bato River Control (Phase II), Bato, Catanduanes

Construction of Bato River Control (Phase II), Bato, Catanduanes is a DPWH-tracked public work in BATO (CATANDUANES), CATANDUANES, Region V. Reported contract value: ₱9,899,996.06. Status: Reported complete (DPWH). Contractor on record: HI-DENSITY INTERNATIONAL CONST AND DEVELOPMENT INC. Figures trace to sumbong.

BATO (CATANDUANES), CATANDUANES, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Sibacungan, Bato, Catanduanes
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Catanduanes District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱9.9M total · 0 flags

4. Implementation

Contract Amount

₱9,899,996.06

Progress

Reported complete (DPWH)

Start Date

September 22, 2023

Target End

January 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.