REHABILITATION/IMPROVEMENT OF DRAINAGE SYSTEM PUROK 2, ZONE 8 UPPER, OUR LADY OF PEACE, BARANGAY CUPANG ANTIPOLO CITY

REHABILITATION/IMPROVEMENT OF DRAINAGE SYSTEM PUROK 2, ZONE 8 UPPER, OUR LADY OF PEACE, BARANGAY CUPANG ANTIPOLO CITY is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱1,920,164.40. Status: Reported complete (DPWH). Contractor on record: LTDL BUILDERS. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-ROXIII-19-0013190 · ₱1,790,228 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19DN0182 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-05-26 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Rizal

Based on the coordinates published with the DPWH record and NOAH file Rizal.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION/IMPROVEMENT OF DRAINAGE SYSTEM PUROK 2, ZONE 8 UPPER, OUR LADY OF PEACE, BARANGAY CUPANG ANTIPOLO CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-19-0013190

₱1,790,228.00 · FY2019

Released to Agusan Pequeño National re High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

195 projects · ₱2.4B total · 0 flags

4. Implementation

Contract Amount

₱1,920,164.40

Progress

Reported complete (DPWH)

Start Date

July 22, 2019

Target End

October 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)RizalCity of AntipoloCupang
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.