Rehabilitation / Major Repair of Flood Control Structure21CC0257

Rehabilitation/ Improvement with Revetment along Malolos River, Catmon to Caingin, Malolos, Bulacan

Rehabilitation/ Improvement with Revetment along Malolos River, Catmon to Caingin, Malolos, Bulacan is a DPWH-tracked public work in BULACAN, Region III. Reported contract value: ₱48,998,928.29. Status: Reported complete (DPWH). Contractor on record: PRECIOUS CONST. Figures trace to sumbong.

BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Major River System and Creek with Flood Control Structure along Barangay Canalate, Malolos, Bulacan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011449

₱130,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013846

₱108,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013831

₱211,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014146

₱17,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007326

₱4,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0001918

₱20,000,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

258 projects · ₱7.9B total · 0 flags

Other projects by this contractor

No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE & SPECIAL SUPPORT PROGRAMCONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITYCONSTRUCTION OF 2ID PERIMETER FENCE AND GATE 1 & 2, PHASE 2,CAMP CAPINPIN, TANAY, RIZAL

Region IV-A, Region IV-A

2020₱127.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SALAPAN ELEMENTARY SCHOOL, SAN JUAN CITY

Metro Manila 1st DEO, National Capital Region

2024₱117.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER 01: CONSTRUCTION OF NEW PUP CAMPUS IN CALOOCAN NORTH, BARANGAY 168, CALOOCAN CITYA. CONSTRUCTION OF NEW POLYTECHNIC UNIVERSITY OF THE PHILIPPINES, BARANGAY 168, CALOOCAN CITYB. CONSTRUCTION OF ADMINISTRATIVE BUILDING - POLYTECHNIC UNIVERSITY

Metro Manila 3rd DEO, National Capital Region

2023₱116.4M
Reported complete (DPWH)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS, TAGAYTAY CALAMBA ROAD VIA CANLUBANG, LAGUNA SECTION, LAGUNA

Region IV-A, Region IV-A

2020₱115.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ALERT MULTI-PURPOSE BUILDING BRGY. MALINTA, VALENZUELA CITY

Metro Manila 3rd DEO, National Capital Region

2020₱100.6M
Reported complete (DPWH)
No sat.

CLUSTER I :A) REPAIR/REHABILITATION/IMPROVEMENT OF LUZONG-TUQUIPA ROAD, BRGYS. LUZONG AND TUQUIPA, LUBA, ABRAB) REPAIR/ REHABILITATION/ IMPROVEMENT OF SITIO CABA-GAYAMAN ROAD, BRGY GAYAMAN, LUBA, ABRAC) REPAIR/REHABILITATION/ IMPROVEMENT OF SABNANGA

Cordillera Administrative Region, Cordillera Administrative Region

2018₱100.0M
Past target date (DPWH On-Going)
View all 258 projects →

4. Implementation

Contract Amount

₱48,998,928.29

Progress

Reported complete (DPWH)

Start Date

January 14, 2022

Target End

September 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.