Construction of Flood Mitigation Structure23CC0252

Construction of Flood Control Structure at Barangay Pagala, Baliuag, Bulacan (K003+161 to K003+461)

Construction of Flood Control Structure at Barangay Pagala, Baliuag, Bulacan (K003+161 to K003+461) is a DPWH-tracked public work in CITY OF BALIUAG (BULACAN), BULACAN, Region III. Reported contract value: ₱71,915,112.64. Status: Reported complete (DPWH). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to sumbong.

CITY OF BALIUAG (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (riprapping) Barangay Igulot, Bocaue, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱71,915,112.64

Progress

Reported complete (DPWH)

Start Date

March 28, 2023

Target End

December 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.