Flood Control and Drainage20OD0037

CONSTRUCTION OF FLOOD CONTROL RIVER WALL ALONG LONGOS CREEK STA.0+000 TO STA. 0+468, BRGY. MALANDAY, VALENZUELA CITY

CONSTRUCTION OF FLOOD CONTROL RIVER WALL ALONG LONGOS CREEK STA.0+000 TO STA. 0+468, BRGY. MALANDAY, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱90,768,063.56. Status: Reported complete (DPWH). Contractor on record: J SIMEON CONST. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱50,000

    Probable match · score 0.90

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20OD0037 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-02-22 → 2021-12-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Flood wall / dike / revetment, cost per linear meter (flood control structure)

₱193,949 per linear m= 0.9x the National Capital Region median (n=45)

Contract cost ₱90,768,064 ÷ 468 linear m read from the DPWH title (“STA.0+000 TO STA. 0+468”; station range length (Sta. a+b to c+d)). National percentile: 72. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · NCR, Third District

Based on the coordinates published with the DPWH record and NOAH file Metro Manila.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD CONTROL RIVER WALL ALONG LONGOS CREEK STA.0+000 TO STA. 0+468, BRGY. MALANDAY, VALENZUELA CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Lamesa Creek (Phase II), Brgy. Ugong, Valenzuela City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Metro Manila 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱90,768,063.56

Progress

Reported complete (DPWH)

Start Date

November 27, 2020

Target End

September 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of ValenzuelaColoong
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.