Construction of Flood Mitigation Structure23CG0073

Construction of Flood Mitigation Structure Improvement and Construction of Concrete Slope Protection work at Maasim River, Phase I, barangay Bahay Pare, Candaba, Pampanga

Construction of Flood Mitigation Structure Improvement and Construction of Concrete Slope Protection work at Maasim River, Phase I, barangay Bahay Pare, Candaba, Pampanga is a DPWH-tracked public work in CANDABA (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱68,321,524.36. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST & TRADING INC FOR: STO CRISTO CONST & TRADING. Figures trace to sumbong.

CANDABA (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Maintenance of Flood Mitigation Structures along Quitangil River, Magalang, Pampanga - Phase 1
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pampanga 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

View all 55 projects →

4. Implementation

Contract Amount

₱68,321,524.36

Progress

Reported complete (DPWH)

Start Date

April 6, 2023

Target End

January 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.