Flood Control and Drainage21FL0060

REHABILITATION OF DRAINAGE, BARIIS, MATNOG, SORSOGON

REHABILITATION OF DRAINAGE, BARIIS, MATNOG, SORSOGON is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱1,928,004.55. Status: Reported complete (DPWH). Contractor on record: DOUBLE R CONST AND SUPPLY. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2021 · ₱11,550

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21FL0060 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-05-28 → 2022-10-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Sorsogon

Based on the coordinates published with the DPWH record and NOAH file Sorsogon.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF DRAINAGE, BARIIS, MATNOG, SORSOGON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱11,550,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Culasi, Matnog, Sorsogon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Sorsogon 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,928,004.55

Progress

Reported complete (DPWH)

Start Date

April 22, 2021

Target End

July 20, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)SorsogonMatnogBariis
Storms whose wind field reached it
Nokaen 2026Fung-Wong 2025Fengshen 2025Bualoi 2025Man-Yi 2024
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.