Construction of Flood Mitigation Structure23EB0022

Construction of Flood Control Structure along Patrick River, Barangay Tagumpay Section, Sta. 0+000 - Sta. 0+440, Sablayan, Occidental Mindoro

Construction of Flood Control Structure along Patrick River, Barangay Tagumpay Section, Sta. 0+000 - Sta. 0+440, Sablayan, Occidental Mindoro is a DPWH-tracked public work in SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B. Reported contract value: ₱45,079,105.81. Status: Reported complete (DPWH). Contractor on record: F A TORRES CONST. Figures trace to sumbong.

SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Patrick River, Barangay Tagumpay Section, Sta. 0+000 - Sta. 0+440, Sablayan, Occidental Mindoro
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Mindoro Occidental District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱45,079,105.81

Progress

Reported complete (DPWH)

Start Date

February 10, 2023

Target End

September 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.