Rehabilitation / Major Repair of Flood Control Structure23CG0097

Rehabilitation of River Channel & Construction of Concrete Slope Protection of Malisik River Control, Magumbali, Candaba, Pampanga

Rehabilitation of River Channel & Construction of Concrete Slope Protection of Malisik River Control, Magumbali, Candaba, Pampanga is a DPWH-tracked public work in CANDABA (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱91,095,547.48. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST & TRADING INC FOR: STO CRISTO CONST & TRADING. Figures trace to sumbong.

CANDABA (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Maintenance of Flood Mitigation Structures along Quitangil River, Magalang, Pampanga - Phase 1
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pampanga 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

View all 55 projects →

4. Implementation

Contract Amount

₱91,095,547.48

Progress

Reported complete (DPWH)

Start Date

April 24, 2023

Target End

February 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.