Construction of Flood Mitigation Structure23CF0043

Construction of Flood Wall Structure with Secondary Road along Peñaranda River, Purok Camia B, Barangay Rio Chico, Gen. Tinio, Nueva Ecija

Construction of Flood Wall Structure with Secondary Road along Peñaranda River, Purok Camia B, Barangay Rio Chico, Gen. Tinio, Nueva Ecija is a DPWH-tracked public work in GENERAL TINIO (PAPAYA) (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱94,931,876.77. Status: Reported complete (DPWH). Contractor on record: F-DEY CONST AND TRADING / DGSARM BUILDERS INC FORMERLY: D G SARMENTA CONST. Figures trace to sumbong.

GENERAL TINIO (PAPAYA) (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Rio Chico River, Barangay Macamias, Guimba, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Nueva Ecija 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱94,931,876.77

Progress

Reported complete (DPWH)

Start Date

February 23, 2023

Target End

December 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.