Flood Control and Drainage18OC0050

CONSTRUCTION OF REVETMENT WALL ALONG ESTERO TRIPA DE GALLINA, BARANGAY PIO DEL PILAR, DISTRICT I, MAKATI CITY, METRO MANILA

CONSTRUCTION OF REVETMENT WALL ALONG ESTERO TRIPA DE GALLINA, BARANGAY PIO DEL PILAR, DISTRICT I, MAKATI CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱29,384,726.08. Status: Reported complete (DPWH). Contractor on record: PRECIOUS CONST. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment Wall along Estero de Tripa de Gallina, Brgy. Pio Del Pilar, Makati City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0026815

₱450,000.00 · FY2018

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Revetment Wall along Estero Tripa

₱27,635,782.80 · PRECIOUS CONSTRUCTION

Contractor

258 projects · ₱7.9B total · 0 flags

Other projects by this contractor

No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE & SPECIAL SUPPORT PROGRAMCONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITYCONSTRUCTION OF 2ID PERIMETER FENCE AND GATE 1 & 2, PHASE 2,CAMP CAPINPIN, TANAY, RIZAL

Region IV-A, Region IV-A

2020₱127.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SALAPAN ELEMENTARY SCHOOL, SAN JUAN CITY

Metro Manila 1st DEO, National Capital Region

2024₱117.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER 01: CONSTRUCTION OF NEW PUP CAMPUS IN CALOOCAN NORTH, BARANGAY 168, CALOOCAN CITYA. CONSTRUCTION OF NEW POLYTECHNIC UNIVERSITY OF THE PHILIPPINES, BARANGAY 168, CALOOCAN CITYB. CONSTRUCTION OF ADMINISTRATIVE BUILDING - POLYTECHNIC UNIVERSITY

Metro Manila 3rd DEO, National Capital Region

2023₱116.4M
Reported complete (DPWH)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS, TAGAYTAY CALAMBA ROAD VIA CANLUBANG, LAGUNA SECTION, LAGUNA

Region IV-A, Region IV-A

2020₱115.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ALERT MULTI-PURPOSE BUILDING BRGY. MALINTA, VALENZUELA CITY

Metro Manila 3rd DEO, National Capital Region

2020₱100.6M
Reported complete (DPWH)
No sat.

CLUSTER I :A) REPAIR/REHABILITATION/IMPROVEMENT OF LUZONG-TUQUIPA ROAD, BRGYS. LUZONG AND TUQUIPA, LUBA, ABRAB) REPAIR/ REHABILITATION/ IMPROVEMENT OF SITIO CABA-GAYAMAN ROAD, BRGY GAYAMAN, LUBA, ABRAC) REPAIR/REHABILITATION/ IMPROVEMENT OF SABNANGA

Cordillera Administrative Region, Cordillera Administrative Region

2018₱100.0M
Past target date (DPWH On-Going)
View all 258 projects →

4. Implementation

Contract Amount

₱29,384,726.08

Progress

Reported complete (DPWH)

Start Date

February 26, 2018

Target End

September 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.