Rehabilitation / Major Repair of Flood Control Structure21CK0034

Rehabilitation of Existing Dike along Tinang River, (Left and Right Bank), Upstream of Sta. Monica Bridge, Concepcion, Tarlac

Rehabilitation of Existing Dike along Tinang River, (Left and Right Bank), Upstream of Sta. Monica Bridge, Concepcion, Tarlac is a DPWH-tracked public work in TARLAC, Region III. Reported contract value: ₱67,548,125.86. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST & TRADING INC FOR: STO CRISTO CONST & TRADING. Figures trace to sumbong.

TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱11,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures Along Tarlac River Control Right Dike, Cardona - Ayson Section, Gerona, Tarlac
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014086

₱35,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005352

₱19,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000291

₱562,425.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007369

₱79,605,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0012520

₱57,605.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000659

₱20,736.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000658

₱246,592.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱67,548,125.86

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

April 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.