15 published flags on records linked to Malis and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Bagbag Creek, Barangay Sta. Cruz, Guiguinto, Bulacan (K003+772 to K003+922)DPWH project · contractor A R L Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Riverbank Protection Structure at Barangay Malis (Phase Iii), Guiguinto, BulacanDPWH project · contractor Wawao Builders
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Flood Control Structures Along Guiguinto River, Malis Section, Guiguinto, BulacanDPWH project · contractor Topnotch Catalyst Builders Inc / Black Hardhat Inc Formerly: Jchardhat Inc
- C7 · High Concurrent Workload for One ContractorSt Timothy Const CorpContractor (applies to all its work) · contractor St Timothy Const Corp
- C7 · High Concurrent Workload for One ContractorGreat Pacific Builders and Gen Contractor IncContractor (applies to all its work) · contractor Great Pacific Builders and Gen Contractor Inc
- C7 · High Concurrent Workload for One ContractorJtc Cruz Const Co IncContractor (applies to all its work) · contractor Jtc Cruz Const Co Inc
- C7 · High Concurrent Workload for One ContractorL R Tiqui Builders IncContractor (applies to all its work) · contractor L R Tiqui Builders Inc
- C7 · High Concurrent Workload for One ContractorTopnotch Catalyst Builders IncContractor (applies to all its work) · contractor Topnotch Catalyst Builders Inc
- C7 · High Concurrent Workload for One ContractorM3 Konstract Corp Formerly:Margarita ConstContractor (applies to all its work) · contractor M3 Konstract Corp Formerly:Margarita Const
- C7 · High Concurrent Workload for One ContractorWawao BuildersContractor (applies to all its work) · contractor Wawao Builders
- C5 · Pattern Consistent with Contract SplittingRehabilitation of Flood Control Structures Along Guiguinto River, Malis Section, Guiguinto, BulacanDPWH project · contractor Topnotch Catalyst Builders Inc / Black Hardhat Inc Formerly: Jchardhat Inc
- C2 · Awards Very Close to the Budget CeilingConstruction of River Control Project Along Guiguinto River, Barangay Malis, Sta. 02+250 - Sta. 02+610, Guiguinto, BulacanDPWH project · contractor A R L Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Bagbag Creek, Barangay Malis, Guiguinto, Bulacan (K004+300 to K004+500)DPWH project · contractor Topnotch Catalyst Builders Inc
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along Guiguinto River, Malis Section, Guiguinto, BulacanDPWH project · contractor Wawao Builders
- A6 · Low-Graded DPWH Contractor Winning DepEd/DOH WorksWawao BuildersContractor (applies to all its work) · contractor Wawao Builders
Named parties may reply or request a correction. See the methodology.