Pumping stations in the public record: ₱26.6 billion in DPWH contracts since 2016, 80% of it in Metro Manila

After the President ordered tighter security at Metro Manila pumping stations, we searched contract, PhilGEPS and budget records. There are 370 DPWH pumping-station contracts, yearly value rose from ₱0.68 billion in 2020 to ₱5.11 billion in 2025, and the Diokno upgrade record still reads "For Procurement."

By

Published · 9 min read · Data as of October 26, 2026

Flat editorial illustration of a flood pumping station: a city canal flows into a pump house with blue pumps and a red cable coil, and pipes discharge water over a seawall into the bay, with stacked gold coins along the canal and rain clouds over low-rise buildings.
Illustration generated by AI

President Ferdinand Marcos Jr. has ordered tighter security at Metro Manila's flood pumping stations after components were reported taken from the Diokno pumping station in Pasay, The Manila Times reported on October 25. According to the report, more Philippine Coast Guard personnel will be deployed, and the contractor will replace the affected components at no cost to the government. The Chronicle noted that the Metropolitan Manila Development Authority (MMDA) runs 73 pumping stations across the capital. The Philippine Daily Inquirer reported that the components were valued at about ₱183,000, and that Coast Guard personnel are posted at the Diokno, Remedios, Abad, Faura, Luneta and Harbor stations along Manila Bay. A week earlier, ABS-CBN News reported that armed Coast Guard personnel would guard several stations after repeated theft cases.

The security story is for the police and the courts. This article covers a different question: what do the public records say about how much has been spent building and upgrading pumping stations, and where? We searched every Department of Public Works and Highways (DPWH) contract record on this site, the PhilGEPS award records and the General Appropriations Act (GAA) lines for the words "pumping station". Below is what we found.

The short version

  • 370 DPWH contracts from 2016 to 2025 mention a pumping station in the title or description. Together they are recorded at ₱26.64 billion.
  • About 80% of that value is in Metro Manila. 234 contracts (₱15.50 billion) are under NCR district offices, and another 33 (₱5.81 billion) are under the DPWH Central Office, mostly for large Metro Manila stations.
  • Yearly contract value rose from ₱0.68 billion in 2020 to ₱5.11 billion in 2025.
  • 139 of 343 contracts that list both a cost and an Approved Budget for the Contract (ABC) are recorded at 99.5% or more of the ABC, and 61 are recorded above it.
  • 302 GAA lines from FY2020 to FY2025 mention a pumping station. They total ₱22.81 billion, and 58 of them are exactly ₱100 million.
  • The record for the Diokno pumping station upgrade (₱115.80 million ABC, contract 24OH0115) still shows "For Procurement" on our latest snapshot, although the DPWH portal lists an award date of November 29, 2024.

Contract value by year

The table counts DPWH contracts whose title or description mentions a pumping station, by infrastructure year. Amounts are recorded contract costs. Contracts still for procurement are recorded at zero.

YearContractsRecorded cost
201624₱0.65B
201728₱2.17B
201820₱3.06B
201921₱1.18B
202013₱0.68B
202123₱2.00B
202251₱4.14B
202344₱2.75B
202485₱4.89B
202561₱5.11B
Total370₱26.64B

The busiest years were 2024, with 85 contracts, and 2025, with 61. The largest single contract is ₱640.7 million, a 2017 pumping station on Estero de Sunog Apog in Manila, which is recorded as completed. Other large contracts include stations in Maytunas (2018, ₱519.4 million), Catmon in Malabon (2019, ₱416.4 million), Malanday on the Pasig-Marikina River (2017, ₱399.5 million), Balut in Tondo (2018, ₱390.9 million), Tapayan in Taguig (2022, ₱389.3 million) and North Navotas (2021, ₱382.4 million).

Where the money went

Region in the recordContractsRecorded cost
National Capital Region234₱15,496.6M
DPWH Central Office33₱5,808.4M
Central Luzon (Region III)60₱3,170.4M
Zamboanga Peninsula (Region IX)9₱1,154.6M
Calabarzon (Region IV-A)4₱250.1M
Central Visayas (Region VII)20₱232.2M
Six other regions combined10₱527.9M

That pumping stations cluster in Metro Manila is expected. Much of the capital is low-lying, especially along Manila Bay and in the Camanava area (Caloocan, Malabon, Navotas and Valenzuela), and its esteros cannot drain by gravity at high tide. Region is the DPWH office that recorded the contract, so a Central Office contract may be for a station anywhere.

Status of the contracts

Status in the recordContractsRecorded cost
Completed248₱16,078.4M
On-Going84₱9,852.4M
Not Yet Started9₱643.1M
For Procurement23₱0 (not yet awarded in the record)
Terminated6₱66.5M

Most on-going contracts are from 2024 (31) and 2025 (37). A few older contracts are still marked on-going. These include a 2017 Pasig-Marikina River contract recorded at 95% progress, two 2018 contracts at 61% and 19%, and two 2019 Navotas coastal dike stations at 92%. Status fields are only as current as DPWH's last update, so an older "on-going" label can simply mean the record was never updated.

The Manila Bay stations in the news

These are the DPWH records we could match to the stations named in recent reports. Ratios compare the recorded cost with the ABC.

RecordYearRecorded costABCCost ÷ ABCStatus
Luneta pumping station upgrading (19OH0024)2019₱9.54M₱10.09M94.5%Completed
Remedios flood mitigation facility: sump pit and pump (19OH0016)2019₱96.50M₱98.00M98.5%Completed
Harbor View pumping station, Phase I2023₱96.50M₱96.50M99.99%Completed
Harbor View pumping station, Phase II2023₱96.50M₱96.50M99.99%Completed
Luneta pumping station (Katigbak Parkway), Phase I2024₱96.49M₱96.50M99.99%Completed
Luneta pumping station (Katigbak Parkway), Phase II2024₱96.49M₱96.50M99.99%Completed
Manila Baywalk outfalls and pumping stations, Remedios and Abad (24O00226)2024₱34.11M₱34.82M98.0%Not Yet Started
Diokno pumping station upgrading, Pasay (24OH0115)2024—₱115.80M—For Procurement

Two points in this table are worth noting.

The Diokno record. Our snapshot of the DPWH Transparency portal lists contract 24OH0115, "Upgrading of Diokno Pumping Station, Pasay City," as "For Procurement." The same record also gives an award amount of ₱114.53 million and an award date of November 29, 2024. These two fields do not match. The likeliest explanation is a status field that was not updated after award. We have not confirmed whether this contract is the one covering the components to be replaced. Readers can check the official portal entry.

Paired phases at about ₱96.5 million. Harbor View and Luneta were each upgraded in two phases in the same year, and every phase is recorded at about ₱96.5 million, within ₱10,000 of its ceiling. This pattern is common across the dataset: 29 pumping-station contracts are recorded between ₱96.0 million and ₱96.5 million, and 82 titles include the word "Phase". Large stations are often funded in yearly tranches, and fixed budget lines, many of them ₱100 million in the GAA (see below), produce ceilings of similar size. Splitting a large station into phases is a normal funding practice. It also means each phase is worth tracking on its own.

How close to the ceiling?

Of the 343 pumping-station contracts that list both a cost and an ABC:

  • 139 (40.5%) are recorded at 99.5% or more of the ABC;
  • 61 (17.8%) are recorded above the ABC;
  • the median contract is recorded at 98.5% of its ABC.

For comparison, of all 241,159 contract records on this site from 2016 to 2025 with both figures, 40.0% are at 99.5% or more of the ABC and 4.4% are above it. Among records the DPWH classifies as "Flood Control Structures," 70.4% are at 99.5% or more of the ABC.

So pumping stations come in close to their ceilings about as often as public works overall. They are recorded above the ceiling about four times as often. A recorded cost above the ABC can come from approved variation orders, price adjustments, an ABC that was revised after the record was created, or data entry. Under procurement rules, bids above the ABC are not accepted, so the gap usually reflects something that happened after the award. Each case needs the contract documents to explain it.

What PhilGEPS shows

PhilGEPS, the government's procurement portal, carries award notices from every agency, not just the DPWH. Titles in the data we hold that mention a pumping station include:

Procuring agencyAwardsTotal
DPWH51₱4,115.4M
MMDA7₱409.1M
Pasig City9₱74.4M
Pasay City5₱66.8M
Navotas City13₱53.8M
National Irrigation Administration14₱44.3M

The MMDA's seven awards run from 2010 to 2024. They include two 2012 San Juan stations with drainage improvements, at Balong Bato (₱139.96 million) and Salapan (₱154.92 million), and a November 2024 emergency purchase of ₱5.00 million in diesel fuel "for the continuous operations of various pumping stations." Many routine MMDA maintenance, repair and security contracts likely carry titles that do not use the words "pumping station," so this count is a floor, not a full picture. Water districts also buy "pumping stations," but those are for water supply, not flood drainage, and are left out of the table above.

What the budget says

The GAA is where Congress authorizes the money. Lines that mention a pumping station:

Fiscal yearGAA linesTotal
FY202025₱1.39B
FY202144₱2.67B
FY202254₱4.65B
FY202343₱2.62B
FY202474₱4.94B
FY202562₱6.54B
Total302₱22.81B

Of these, 287 lines are in the DPWH budget and 15 are in allocations to local government units. Fifty-eight lines are exactly ₱100 million and 29 are exactly ₱50 million. The largest FY2025 lines are ₱400 million for Phase 2 of the San Andres pumping station and ₱300 million for Phase 1 of the Cutcut pumping station in Pasay. Budget lines and contracts do not match one to one, because a line may fund work described differently in the contract. Still, both series moved together: the FY2025 lines (₱6.54 billion) and 2025 contracts (₱5.11 billion) are the highest in the six-year window.

For more on how the GAA is built, see our national budget explainer. For DPWH flood spending more broadly, see the flood-control explainer.

What residents and reporters can check

  1. Look up your station. Search the station name on the search page or find it on the map. Each record links to the DPWH Transparency portal entry.
  2. Compare status with what you see. A station marked completed that is not running, or one marked on-going for years, is worth reporting through Submit a tip.
  3. Ask for the as-built documents. Contract documents, variation orders and acceptance certificates can be requested through eFOI. These explain most cost-above-ceiling cases.
  4. Follow the operator. The MMDA operates 73 pumping stations, according to The Chronicle. Its maintenance and security contracts should appear on PhilGEPS.

Our automated checks have raised indicators on several pumping-station records. These have been reviewed and published:

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Right of reply

These figures describe public contract, procurement and budget records, not the conduct of any person or company. The DPWH, its district engineering offices, the MMDA, the local governments named here, and any contractor connected to these records may respond or correct the record. Use our contact form or the dispute link on any indicator page. Responses are published with the record.

Data as of October 26, 2026. Contract records are from the DPWH Transparency portal and related public datasets as stored on this site. Award records are from PhilGEPS. Budget lines are from DBM's published GAA files for FY2020–FY2025. News on pumping-station security is as reported by The Manila Times and The Chronicle (October 25, 2026), the Philippine Daily Inquirer, and ABS-CBN News (October 19, 2026).

Sources

  1. The Manila Times: Marcos orders tighter security at pumping stations after cable theft — Dizon (Oct 25, 2026)
  2. The Chronicle: PBBM orders tighter security at pumping stations following cable theft (Oct 25, 2026)
  3. Philippine Daily Inquirer: Report on components taken from the Diokno pumping station
  4. ABS-CBN News: Armed PCG personnel to guard several pumping stations following repeated theft cases (Oct 19, 2026)
  5. DPWH Transparency portal: contract 24OH0115, Upgrading of Diokno Pumping Station, Pasay City
  6. DPWH Transparency portal: contract 24O00226, Manila Baywalk outfalls and pumping stations (Remedios and Abad)