Flood Control and Drainage21FN0043

CONSTRUCTION/IMPROVEMENT OF RIVERBANK SLOPE PROTECTION, DOWNSTREAM OF MALAWAG BRIDGE, MALAWAG, NABUA, CAMARINES SUR

CONSTRUCTION/IMPROVEMENT OF RIVERBANK SLOPE PROTECTION, DOWNSTREAM OF MALAWAG BRIDGE, MALAWAG, NABUA, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱44,784,280.23. Status: Reported complete (DPWH). Contractor on record: RICHMAR CONST 18797. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱42,118,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Contol Structure Along Barit River, Downstream of Cagas Bridge, Nabua, Camarines Sur
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱404,461,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 18797

27 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱44,784,280.23

Progress

Reported complete (DPWH)

Start Date

February 19, 2021

Target End

September 4, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.