Construction of Flood Mitigation Structure23IE0055

Construction of Silad Tide Embankment (Left Side), Brgy. Silad, Villaba, Leyte

Construction of Silad Tide Embankment (Left Side), Brgy. Silad, Villaba, Leyte is a DPWH-tracked public work in VILLABA (LEYTE), LEYTE, Region VIII. Reported contract value: ₱48,754,995.16. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP. Figures trace to sumbong.

VILLABA (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation, Barangay Hinabuyan, Villaba, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-23-0026134

₱1,536,561.00 · FY2023

Released to 0000000 Surigao del Norte - State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

692 projects · ₱17.7B total · 35 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱48,754,995.16

Progress

Reported complete (DPWH)

Start Date

May 4, 2023

Target End

March 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.