Construction of Flood Mitigation Structure24IE0036

Construction of Flood Control Structure (Caigit to Pangas), Barangay Poblacion Del Norte, Villaba, Leyte

Construction of Flood Control Structure (Caigit to Pangas), Barangay Poblacion Del Norte, Villaba, Leyte is a DPWH-tracked public work in VILLABA (LEYTE), LEYTE, Region VIII. Reported contract value: ₱48,754,998.58. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP. Figures trace to sumbong.

VILLABA (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Caigit to Pangas ) , Barangay Poblacion Del Norte, Villaba, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008528

₱1,364,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0002927

₱372,370.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0017753

₱225,304.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008531

₱126,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0017646

₱72,102.00 · FY2024

Source

Office-level release, not tied to this specific contract

NCA NCA-ROXI-24-0001110

₱193,444.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

692 projects · ₱17.7B total · 35 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱48,754,998.58

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

December 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.