Construction of Flood Mitigation Structure22I00040

Construction of Flood Control, Brgy. Belen, Leyte, Leyte

Construction of Flood Control, Brgy. Belen, Leyte, Leyte is a DPWH-tracked public work in LEYTE (LEYTE), LEYTE, Region VIII. Reported contract value: ₱190,871,336.40. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC / JGO BUILDERS. Figures trace to sumbong.

LEYTE (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Poblacion 1, Hindang, Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003140

₱492,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0011484

₱20,590.00 · FY2022

Released to Bicol University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱190.9M total · 0 flags

4. Implementation

Contract Amount

₱190,871,336.40

Progress

Reported complete (DPWH)

Start Date

March 7, 2022

Target End

September 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.