Construction of Flood Mitigation Structure23G00066

Construction of Seawall (Section 6), Iloilo City

Construction of Seawall (Section 6), Iloilo City is a DPWH-tracked public work in ILOILO CITY (CAPITAL) (ILOILO), ILOILO, Region VI. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST & SUPPLY INC FORMERLY: ADP CONST & SUPPLY. Figures trace to sumbong.

ILOILO CITY (CAPITAL) (ILOILO), ILOILO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Jalaur River, Calinog, Iloilo
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-23-0027033

₱629,204.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

August 23, 2023

Target End

November 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.