Construction of Flood Mitigation Structure23GI0029

Construction of Aganan Flood Control Structure (Jaro-Aganan River), Barangay Bagumbayan, Alimodian, Iloilo

Construction of Aganan Flood Control Structure (Jaro-Aganan River), Barangay Bagumbayan, Alimodian, Iloilo is a DPWH-tracked public work in ALIMODIAN (ILOILO), ILOILO, Region VI. Reported contract value: ₱96,499,785.68. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST & SUPPLY INC FORMERLY: ADP CONST & SUPPLY. Figures trace to sumbong.

ALIMODIAN (ILOILO), ILOILO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Anono-o Flood Control Project, Barangay Anono-o, Guimbal, Iloilo
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-23-0022703

₱161,496.00 · FY2023

Released to 0300006 Regional Office VI - - (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,785.68

Progress

Reported complete (DPWH)

Start Date

February 10, 2023

Target End

October 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.