Construction of Flood Mitigation Structure23BH0148

Construction of Flood Control Structure, Barangay Arubub, Section 2, Jones, Isabela

Construction of Flood Control Structure, Barangay Arubub, Section 2, Jones, Isabela is a DPWH-tracked public work in JONES (ISABELA), ISABELA, Region II. Reported contract value: ₱96,489,771.32. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING & DEVELOPMENT SERVICES. Figures trace to sumbong.

JONES (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Barangay I Flood Control Structure, Sta. 0+000 - Sta. 0+350, Jones, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-23-0022537

₱0.00 · FY2023

Released to 0300008 Regional Office VIII - - (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

83 projects · ₱5.7B total · 15 flags

4. Implementation

Contract Amount

₱96,489,771.32

Progress

Reported complete (DPWH)

Start Date

April 17, 2023

Target End

February 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.