Flood Control and Drainage25IF0014

CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE CAGBULO RIVER, ALBUERA, LEYTE

CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE CAGBULO RIVER, ALBUERA, LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱48,148,674.99. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JM COLLERA KONSTRACT. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱60,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Limbuhan River, Barangay Cantariwis, Tolosa, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-25-0008523

₱130,620,055.00 · FY2025

Released to Central Philippines State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,148,674.99

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 26, 2025

Target End

October 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.