Flood Control and Drainage24I00099

CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN BARANGAY CAN-ABONG, BORONGAN CITY, EASTERN SAMAR LD

CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN BARANGAY CAN-ABONG, BORONGAN CITY, EASTERN SAMAR LD is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱144,652,553.86. Status: Past target date (DPWH On-Going). Contractor on record: JGO BUILDERS. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

84 projects · ₱3.9B total · 1 flags

4. Implementation

Contract Amount

₱144,652,553.86

Progress

Past target date (DPWH On-Going)

Start Date

April 1, 2024

Target End

June 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.