Flood Control and Drainage24CL0014

CONSTRUCTION OF FLOOD CONTROL TAUGTOG - MAMBOG - BANCAL RIVER PHASE 1-A, BOTOLAN, ZAMBALES

CONSTRUCTION OF FLOOD CONTROL TAUGTOG - MAMBOG - BANCAL RIVER PHASE 1-A, BOTOLAN, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱86,847,876.46. Status: Reported complete (DPWH). Contractor on record: R A PAHATI CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROIVB-24-0008180 · ₱217,502 · release to the district office, not itemized per project

    Possible match · score 0.56

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24CL0014 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-11-16 → 2025-03-15

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Zambales

Based on the coordinates published with the DPWH record and NOAH file Zambales.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD CONTROL TAUGTOG - MAMBOG - BANCAL RIVER PHASE 1-A, BOTOLAN, ZAMBALES

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gama River Slope Protection / Flood Control Structure Phase 2, Sta. Cruz, Zambales
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-24-0008180

₱217,502.00 · FY2024

Released to President Diosdado Macapagal Memorial National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱86,847,876.46

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

December 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)ZambalesBotolanTaugtog
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Kajiki 2025Co-May 2025
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.