Construction of Flood Mitigation Structure24GK0004

Construction of Flood Control Structure along Lag-asan River, Cadiz City, Negros Occidental

Construction of Flood Control Structure along Lag-asan River, Cadiz City, Negros Occidental is a DPWH-tracked public work in CADIZ CITY (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI. Reported contract value: ₱48,997,432.14. Status: Reported complete (DPWH). Contractor on record: SILVERGRACES CONST AND CONST SUPPLY. Figures trace to sumbong.

CADIZ CITY (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Minabuno River, Cadiz City, Negros Occidental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-24-0014212

₱2,977,141.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007641

₱2,046,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0005549

₱263,627.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0001414

₱218,533.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007643

₱189,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,997,432.14

Progress

Reported complete (DPWH)

Start Date

March 13, 2024

Target End

September 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.