Construction of Flood Mitigation Structure22ED0011

Construction of Flood Mitigating Structure along Mag-Asawang Tubig River, Sta. 0+000 - Sta. 0+242 U/S, Sta. 0+000 - Sta. 0+123 D/S, San Andres Putik, Naujan, Oriental Mindoro

Construction of Flood Mitigating Structure along Mag-Asawang Tubig River, Sta. 0+000 - Sta. 0+242 U/S, Sta. 0+000 - Sta. 0+123 D/S, San Andres Putik, Naujan, Oriental Mindoro is a DPWH-tracked public work in NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱48,999,957.50. Status: Reported complete (DPWH). Contractor on record: ALBERTO UY CONST & DEVELOPMENT. Figures trace to sumbong.

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigating Structure along Mag-Asawang Tubig River, Sta. 0+000 - Sta. 0+360, San Andres Putik, Naujan, Oriental Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-22-0006020

₱10,595,397.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002356

₱1,389,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002909

₱866,223,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002986

₱150,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002621

₱2,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,957.50

Progress

Reported complete (DPWH)

Start Date

May 23, 2022

Target End

January 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.