Construction of Flood Mitigation Structure24FN0005

Construction of Riverbank Protection Structure along Bicol River, Barangay La Purisima Section, Nabua, Camarines Sur

Construction of Riverbank Protection Structure along Bicol River, Barangay La Purisima Section, Nabua, Camarines Sur is a DPWH-tracked public work in NABUA (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: BICOL GOLDROCK CONST CORP. Figures trace to sumbong.

NABUA (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Burabod Creek, Tigaon, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0010936

₱1,454,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0003580

₱482,055.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0010938

₱134,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

February 21, 2024

Target End

December 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.