Flood Control and Drainage21FC0128

REHABILITATION / IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG LANITON BRIDGE IN BARANGAY LANITON, BASUD, CAMARINES NORTE

REHABILITATION / IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG LANITON BRIDGE IN BARANGAY LANITON, BASUD, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱16,667,715.70. Status: Past target date (DPWH On-Going). Contractor on record: WIZARD CONCRETE SOLUTIONS AND CONST CORP FORMERLY: WIZARD TRADING & CONST 21921. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱43,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Structures along Laniton Bridge in Barangay Laniton, Basud, Camarines Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Camarines Norte DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱16,667,715.70

Progress

Past target date (DPWH On-Going)

Start Date

June 22, 2021

Target End

December 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.