Construction of Flood Mitigation Structure23CC0099

Construction of River Control Project along Guiguinto River, Barangay Malis, Sta. 02+250 - Sta. 02+610, Guiguinto, Bulacan

Construction of River Control Project along Guiguinto River, Barangay Malis, Sta. 02+250 - Sta. 02+610, Guiguinto, Bulacan is a DPWH-tracked public work in GUIGUINTO (BULACAN), BULACAN, Region III. Reported contract value: ₱96,499,623.93. Status: Reported complete (DPWH). Contractor on record: A R L CONST. Figures trace to sumbong.

GUIGUINTO (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Guiguinto River, Poblacion, Guiguinto, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,623.93

Progress

Reported complete (DPWH)

Start Date

February 13, 2023

Target End

February 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.