Rehabilitation / Major Repair of Flood Control Structure20F00106

Rehabilitation/Reconstruction of Flood Control Structure along Managa-naga River, Bulan, Sorsogon

Rehabilitation/Reconstruction of Flood Control Structure along Managa-naga River, Bulan, Sorsogon is a DPWH-tracked public work in SORSOGON, Region V. Reported contract value: ₱144,749,727.70. Status: Reported complete (DPWH). Contractor on record: CENTERWAYS CONST AND DEVELOPMENT INC / L BROS CONST AND SUPPLY INC FORMERLY: L BROS CONST & SUPPLY. Figures trace to sumbong.

SORSOGON, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱8,800,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Incarizan River, Magallanes, Sorsogon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007845

₱102,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013810

₱57,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010143

₱30,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013817

₱18,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014088

₱10,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱144,749,727.70

Progress

Reported complete (DPWH)

Start Date

December 11, 2020

Target End

October 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.