Flood Control and Drainage25IC0073

REHABILITATION OF FLOOD CONTROL STRUCTURE, CROSS DRAIN AND LINGAYON SPILLWAY ALONG ASTORGA ACCESS ROAD, BARANGAY ASTORGA, ALANGALANG, LEYTE

REHABILITATION OF FLOOD CONTROL STRUCTURE, CROSS DRAIN AND LINGAYON SPILLWAY ALONG ASTORGA ACCESS ROAD, BARANGAY ASTORGA, ALANGALANG, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱14,675,402.59. Status: Past target date (DPWH On-Going). Contractor on record: KAUIE BUILDERS. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure, Cross Drain and Lingayon Spillway along Astorga Access Road, Barangay Astorga, Alangalang, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

258 projects · ₱2.7B total · 0 flags

4. Implementation

Contract Amount

₱14,675,402.59

Progress

Past target date (DPWH On-Going)

Start Date

March 24, 2025

Target End

July 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.