GAA 2025 OO-225IJ0017

OO2: CONTRUCTION OF FLOOD CONTROL STRUCTURE ALONG GANDARA RIVER, PHASE II, BARANGAY PIZARRO, GANDARA, SAMAR

OO2: CONTRUCTION OF FLOOD CONTROL STRUCTURE ALONG GANDARA RIVER, PHASE II, BARANGAY PIZARRO, GANDARA, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱42,817,925.42. Status: Past target date (DPWH On-Going). Contractor on record: ETAN CONST 39761. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱43,737,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Gandara River, Phase II, Barangay Pizarro, Gandara, Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Samar 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 39761

133 projects · ₱4.1B total · 0 flags

4. Implementation

Contract Amount

₱42,817,925.42

Progress

Past target date (DPWH On-Going)

Start Date

March 6, 2025

Target End

November 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.