Rehabilitation / Major Repair of Flood Control Structure24CK0080

Rehabilitation of Existing Dike along Parua River (Talimundoc-Marimla Section, Right Bank), Package A, Concepcion, Tarlac

Rehabilitation of Existing Dike along Parua River (Talimundoc-Marimla Section, Right Bank), Package A, Concepcion, Tarlac is a DPWH-tracked public work in CONCEPCION (TARLAC), TARLAC, Region III. Reported contract value: ₱96,494,656.20. Status: Reported complete (DPWH). Contractor on record: JAGONBUILD CONST CORP FOR JAGON BUILDERS. Figures trace to sumbong.

CONCEPCION (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tarlac River Control ( Right Dike ) , Villa Paz - Dicolor Section, Gerona, Tarlac
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008260

₱1,425,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008262

₱132,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,494,656.20

Progress

Reported complete (DPWH)

Start Date

March 16, 2024

Target End

October 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.