Construction of Flood Mitigation Structure22CL0080

Construction of Flood Mitigation Structure,Tambak River (Upstream) Phase IV, Iba, Zambales

Construction of Flood Mitigation Structure,Tambak River (Upstream) Phase IV, Iba, Zambales is a DPWH-tracked public work in IBA (CAPITAL) (ZAMBALES), ZAMBALES, Region III. Reported contract value: ₱37,620,000.00. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS & SUPPLY. Figures trace to sumbong.

IBA (CAPITAL) (ZAMBALES), ZAMBALES, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure,Tambak River (Upstream) Phase IV, Iba, Zambalesá
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003012

₱392,400,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002822

₱60,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001624

₱3,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱37,620,000.00

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

September 30, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.