Construction of Flood Mitigation Structure23GA0102

Construction of Flood Control / Revetment Wall along Aklan River, Barangay Sigcay, Banga, Aklan

Construction of Flood Control / Revetment Wall along Aklan River, Barangay Sigcay, Banga, Aklan is a DPWH-tracked public work in BANGA (AKLAN), AKLAN, Region VI. Reported contract value: ₱48,999,545.82. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST & SUPPLY INC FORMERLY: ADP CONST & SUPPLY. Figures trace to sumbong.

BANGA (AKLAN), AKLAN, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Revetment Wall along Aklan River, Barangay Sigcay, Banga, Aklan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Aklan District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,545.82

Progress

Reported complete (DPWH)

Start Date

May 4, 2023

Target End

January 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.