Flood Control and Drainage25DO0027

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, KAY BULUTONG CIS, MORONG, RIZ

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, KAY BULUTONG CIS, MORONG, RIZ is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱9,432,006.51. Status: Past target date (DPWH On-Going). Contractor on record: GKB BUILDERS. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Kay Bulutong CIS, Morong, Rizal
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Rizal 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Possible match · 80%

Construction of Roadway Lightings at Brgy. 3rd D

₱12,253,001.63 · GKB BUILDERS

Contractor

22 projects · ₱175.6M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS - SAN MATEO - RODRIGUEZ ROAD - K0023+100 - K0024+000

Rizal 2nd DEO, Region IV-A

2022₱23.5M
Reported complete (DPWH)
No sat.

Construction of Slope Protection Structure along Sakayin Creek at Sitio Namay, Sitio Caingin, and Sitio Wawa, Barangay San Juan, Morong, Rizal

MORONG (RIZAL), RIZAL, Region IV-A

2024₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT UNIVERSITY OF RIZAL SYSTEM (URS), BARANGAY SAN JOSE, ROD.....

Rizal 2nd DEO, Region IV-A

2022₱14.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MANILA EAST ROAD - K0049+592 - K0050+281 BARAS, RIZAL

Rizal 2nd DEO, Region IV-A

2021₱14.2M
Reported complete (DPWH)
No sat.

CONCRETING OF SITIO PULKUM TO SITIO MAY-UGAT, BRGY. LAGUNDI FMR, BRGY. LAGUNDI MORONG, RIZAL

Rizal 2nd DEO, Region IV-A

2024₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, CARDONA, RIZAL

Rizal 2nd DEO, Region IV-A

2023₱9.9M
Reported complete (DPWH)
View all 22 projects →

4. Implementation

Contract Amount

₱9,432,006.51

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2025

Target End

May 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.