Flood Control and Drainage25IM0040

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN ROQUE RIVER, PHASE 2, TACLOBAN CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN ROQUE RIVER, PHASE 2, TACLOBAN CITY is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱144,641,644.39. Status: Past target date (DPWH On-Going). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST 11555. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Drainage), Barangay 95 Caibaan, Tacloban City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Tacloban City DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 11555

239 projects · ₱17.7B total · 0 flags

4. Implementation

Contract Amount

₱144,641,644.39

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

January 8, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.