Flood Control and Drainage24DN0029

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CALAWIS CREEK PHASE 2, BARANGAY CALAWIS ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CALAWIS CREEK PHASE 2, BARANGAY CALAWIS ANTIPOLO CITY, RIZAL (SECOND DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱48,999,849.23. Status: Reported complete (DPWH). Contractor on record: 1C4M BUILDERS INC. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Calawis Creek Phase 2, Barangay Calawis, Antipolo City, Rizal
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Rizal 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

65 projects · ₱1.6B total · 1 flags

4. Implementation

Contract Amount

₱48,999,849.23

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

November 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.