Flood Control and Drainage25DM0074

CONSTRUCTION OF REVETMENT WALL AT BARANGAY POBLACION ALONG MULANAY RIVER, MULANAY, QUEZON

CONSTRUCTION OF REVETMENT WALL AT BARANGAY POBLACION ALONG MULANAY RIVER, MULANAY, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱48,019,995.94. Status: Past target date (DPWH On-Going). Contractor on record: R A MENDIOLA CONST & DEVELOPER. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control with Baywalk of Brgy. Masipag to Brgy Pagasa along Macalelon River, Macalelon, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,019,995.94

Progress

Past target date (DPWH On-Going)

Start Date

March 3, 2025

Target End

October 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.