Construction of Flood Mitigation Structure22CJ0172

Construction of Camiling-Agno River Floodway Phase 2, Tarlac

Construction of Camiling-Agno River Floodway Phase 2, Tarlac is a DPWH-tracked public work in CAMILING (TARLAC), TARLAC, Region III. Reported contract value: ₱94,473,500.00. Status: Reported complete (DPWH). Contractor on record: ROYAL CROWN MONARCH CONST & SUPPLIES CORP. Figures trace to sumbong.

CAMILING (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Camiling River Left Bank Phase II-2, Poblacion D to G Section, Poblacion D to G, Camiling, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002780

₱96,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0007963

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002637

₱45,500,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002923

₱905,900,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002619

₱14,400,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002641

₱10,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002789

₱35,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱94,473,500.00

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

March 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.