GAA 2025 SSP25CJ0165

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG CAMILING RIVER CUBCUB SECTION, CUBCUB, MAYANTOC, TARLAC (PACKAGE 3)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG CAMILING RIVER CUBCUB SECTION, CUBCUB, MAYANTOC, TARLAC (PACKAGE 3) is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱74,250,000.00. Status: Reported complete (DPWH). Contractor on record: RD8 BUILDERS CORP UNDER THE NAME OF RD8 BUILDERS. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱75,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Camiling River Cubcub Section, Cubcub, Mayantoc, Tarlac (Package 3)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Tarlac DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

94 projects · ₱2.6B total · 3 flags

Other projects by this contractor

View all 94 projects →

4. Implementation

Contract Amount

₱74,250,000.00

Progress

Reported complete (DPWH)

Start Date

April 8, 2025

Target End

November 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.