Construction of Flood Mitigation Structure24A00152

Construction of Flood Control Structure Along Aringay River, Barangay Anduyan, Tubao, La Union

Construction of Flood Control Structure Along Aringay River, Barangay Anduyan, Tubao, La Union is a DPWH-tracked public work in TUBAO (LA UNION), LA UNION, Region I. Reported contract value: ₱144,749,869.10. Status: Reported complete (DPWH). Contractor on record: RODEKOM GEN CONST AND ENT. Figures trace to sumbong.

TUBAO (LA UNION), LA UNION, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aringay River Basin, Brgy. Anduyan, Tubao, La Union
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007428

₱1,468,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007429

₱136,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0001848

₱66,413.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱144,749,869.10

Progress

Reported complete (DPWH)

Start Date

March 15, 2024

Target End

January 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.