Construction of Flood Mitigation Structure24HN0102

Construction of Flood Control Structure along Butuanon River, Phase 5, Barangay Tingub - Barangay Canduman, Mandaue City, Cebu

Construction of Flood Control Structure along Butuanon River, Phase 5, Barangay Tingub - Barangay Canduman, Mandaue City, Cebu is a DPWH-tracked public work in MANDAUE CITY (CEBU), CEBU, Region VII. Reported contract value: ₱57,800,000.00. Status: Reported complete (DPWH). Contractor on record: ZLREJ TRADING AND CONST CORP. Figures trace to sumbong.

MANDAUE CITY (CEBU), CEBU, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cansaga River, Barangay Nangka ( Phase III ) , Consolacion, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0020129

₱32,500,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007558

₱1,366,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0001392

₱538,511.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0018705

₱152,832.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007561

₱126,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱57,800,000.00

Progress

Reported complete (DPWH)

Start Date

March 15, 2024

Target End

December 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.