Flood Control and Drainage19IJ0063

002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG GANDARA RIVER, BRGY. ADELA HEIGHTS, GANDARA, SAMAR

002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG GANDARA RIVER, BRGY. ADELA HEIGHTS, GANDARA, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱61,123,093.31. Status: Reported complete (DPWH). Contractor on record: B VICENCIO BUILDERS BVB INC FORMERLY:B VICENCIO CONST. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-ROX-19-0014080 · ₱895,000 · release to the district office, not itemized per project

    Possible match · score 0.77

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19IJ0063 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-05-21 → 2025-09-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Samar

Based on the coordinates published with the DPWH record and NOAH file Samar.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: 002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG GANDARA RIVER, BRGY. ADELA HEIGHTS, GANDARA, SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROX-19-0014080

₱895,000.00 · FY2019

Released to Suarez National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

358 projects · ₱21.1B total · 2 flags

Other projects by this contractor

No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SAN JUANICO BR) - K0810+134 - K0810+500, K0815+000 - K0815+550, K0817+500 - K

Region VIII, Region VIII

2024₱332.5M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITES - CONSTRUCTION OF JUNCTION NATIONAL ROAD BRGY. CAROLINA, CAN-AVID - DOLORES - MASLOG ROAD, (BRGY. MAGSAYSAY - BRGY. MAGONGBONG - BRGY. GAP-A

Region VIII, Region VIII

2022₱238.6M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR

Region VIII, Region VIII

2019₱236.4M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) K0695+000 - K0696+178, K0697+217 - K0697+533, K0724+748 - K0726+929, SAMAR 1ST

Region VIII, Region VIII

2024₱214.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN STA. FE - SAN MIGUEL ROAD, LEYTE

Region VIII, Region VIII

2024₱192.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPVT. OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS

Region VII, Region VII

2016₱178.0M
Reported complete (DPWH)
View all 358 projects →

4. Implementation

Contract Amount

₱61,123,093.31

Progress

Reported complete (DPWH)

Start Date

June 19, 2019

Target End

February 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)SamarGandaraMinda
Storms whose wind field reached it
Nokaen 2026Koto 2025Fung-Wong 2025Kalmaegi 2025Fengshen 2025
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-11-03El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.