Construction of Flood Mitigation Structure24OH0040

Construction of Drainage System along Libertad Main (From Roxas Blvd to Taft Avenue, Pasay City, Sta 0 + 322 to Sta 0 + 483), Phase 5

Construction of Drainage System along Libertad Main (From Roxas Blvd to Taft Avenue, Pasay City, Sta 0 + 322 to Sta 0 + 483), Phase 5 is a DPWH-tracked public work in PASAY CITY (METROPOLITAN MANILA), PASAY CITY, National Capital Region. Reported contract value: ₱89,071,419.94. Status: Reported complete (DPWH). Contractor on record: AMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to sumbong.

PASAY CITY (METROPOLITAN MANILA), PASAY CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008753

₱1,875,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008767

₱173,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱89,071,419.94

Progress

Reported complete (DPWH)

Start Date

February 21, 2024

Target End

November 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.