Flood Control and Drainage20O00065

REHABILITATION OF SEAWALL ALONG MANILA BAY (PARANAQUE SECTION) PHASE I PARANAQUE

REHABILITATION OF SEAWALL ALONG MANILA BAY (PARANAQUE SECTION) PHASE I PARANAQUE is a DPWH-tracked public work in Flood Control Management Cluster, Central Office. Reported contract value: ₱92,314,101.26. Status: Reported complete (DPWH). Contractor on record: AKN CONST CORP. Figures trace to dpwh.

Flood Control Management Cluster, Central Office
Region: Central Office

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20O00065 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-03-23 → 2022-05-12

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF SEAWALL ALONG MANILA BAY (PARANAQUE SECTION) PHASE I PARANAQUE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

128 projects · ₱7.9B total · 9 flags

4. Implementation

Contract Amount

₱92,314,101.26

Progress

Reported complete (DPWH)

Start Date

January 18, 2021

Target End

December 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of ParañaqueSan Dionisio
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Man-Yi 2024Trami 2024Ewiniar 2024
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.